Level Five WALL & CEILING 604 555 0196

Scope & rates

Four scopes. Rates per square foot of board.

Board square footage, not floor area — walls plus ceilings, less the openings. It is the only unit that means anything, and it is the one your other trades quote in.

Level 4 — paint-ready

$2.82 / sq ft of board

Joints taped and coated, fasteners spotted, beads finished, sanded. The field is bare board. Correct for a matte finish in a room without punishing light, and it is what most of the industry means by "finished".

  • Three coats over tape, feathered out
  • Fasteners spotted three times
  • Beads and trims finished flush
  • Sanded, vacuumed, left ready for primer

Level 5 — skim coated

$4.99 / sq ft of board

Everything in Level 4, then a thin coat of compound over the entire surface. There is then no difference in porosity or texture between a joint and the board beside it. This is not a luxury: it is the only thing that survives raking light off a big window or a run of pot lights set close to a wall.

  • Full skim, wall to wall and corner to corner
  • Priced on area, not on joints, because that is how it is done
  • Right for gloss, semi-gloss and any deep colour
  • What we quote by default on residential

Architectural

$8.50 / sq ft of board

Where the drawings have no trim on them. Shadow-gap reveals instead of cornice, drywall returns at the openings instead of casing, radius corners, barrel vaults, flush bases. Slow, skilled, and unforgiving — there is no moulding to hide behind.

  • Reveal beads set dead straight over the full run
  • Drywall returns at windows and doors, four finished corners each
  • Radius and curved work, usually two layers of ¼" bent wet
  • Continuous planes where the architect will not accept a control joint

Acoustic assemblies

quoted per assembly

Separation between bedrooms, media rooms and mechanical. Double ⅝" with a damping compound between the layers, resilient channel, or a proprietary board. Different material, different labour, and it has to be sequenced with the trades either side of us.

  • Double ⅝" with damping compound
  • Resilient channel over the studs
  • Perimeter sealed — the detail that actually makes it work
  • We will tell you when it is not worth the money

What moves a rate

Ceiling height
Past nine feet you are off a stepladder; past ten you are on stilts or staging. That changes the labour rate rather than the quantity, so it is a multiplier: 12% over 9 ft, 25% over 10 ft.
Ceilings against walls
Overhead work, a board lifter, more fasteners. A 15% factor on the ceiling area, not a blended rate across the job.
Openings
A window is not a saving. It is four finished corners and a run of bead. If the drawings call for a drywall return instead of casing, it is a great deal more than that.
The framing you hand us
We check it before we board. If a wall is out enough that a reveal would show it, we will tell you before we start rather than after — and it will cost you a day of shimming instead of a rebuild.
Minimum
$1,800. Below that the mobilisation costs more than the work.

Send us the drawings.

We take off from PDFs and quote in writing, usually inside three working days.